Winning before the Real Estate Regulatory Authority can feel like the finish line—the order is in your hand, the builder has been told to refund your money with interest, and you expect a cheque to follow. Then nothing happens. Weeks pass, the developer stops responding, and you realise an order on paper is not the same as money in your account. The law, however, gives that order real teeth. This blog explains the RERA order execution process from start to finish, how Section 40 of the RERA turns your order into a debt recoverable like a tax arrear, how to obtain a RERA recovery certificate, and your options when a developer simply refuses to pay.

You Won at RERA—Why Isn’t the Money in Your Account?

While a RERA order directing a refund or payment of interest and compensation is binding, it is not self-executing because the authority does not transfer money from the builder to you on its own; thus, someone has to set the recovery machinery in motion. That is the stage most allottees are unprepared for. Once the order attains finality, either because the 60-day window to appeal to the Real Estate Appellate Tribunal has lapsed, or because any appeal has been decided and there is no stay, the order becomes ripe for execution, and the recovery of the RERA award from the builder can begin in earnest.

The Legal Engine: Section 40 of the RERA Act

Section 40 forms the heart of the Real Estate (Regulation and Development) Act, 2016, and it has two pillars. Section 40(1) deals with financial matters; that is, when a promoter fails to pay any interest, penalty, or compensation imposed on it, the sum can be recovered as an arrear of land revenue, which is the same coercive machinery the State uses to collect unpaid land dues. While Section 40(2) pertains to behaviour, where the Authority, Adjudicating Officer, or Appellate Tribunal directs a person to do, or refrain from doing, a particular act, that direction is to be enforced in the manner prescribed by the rules if it is disobeyed. Together, the two sub-sections indicate that both a monetary award and an order  are backed by real enforcement power.

The strength of Section 40(1) lies in what “arrears of land revenue” entails. It is a summary mechanism: you do not have to file a fresh civil suit and prove your claim all over again, because the amount already stands determined by the RERA order. The State’s revenue-recovery apparatus is simply placed at the allottee’s disposal. A nuance matters here, though, as to who determines what. In M/s Newtech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh (2021), the Hon’ble Court held that the Regulatory Authority will itself decide claims for refund, interest on refund, and interest for delayed possession under Section 18, while claims for compensation under Sections 12, 14, 18 and 19 will be  decided by the Adjudicating Officer.

Newtech also settled the question that once threatened to blunt this remedy. A builder had argued that, read literally, Section 40(1) allowed recovery only of interest and penalty, not the principal amount a homebuyer had actually paid. The Supreme Court rejected that narrow reading, holding that it “would defeat the basic purpose of the Act.” Reading Section 40(1) together with Section 18 under which interest does not even begin to run until the principal is determined, the Court treated the principal and interest as a single composite sum and held that the amount invested by the homebuyer, together with interest, was squarely recoverable under Section 40(1). The right to a refund under Section 18, it added, is “unqualified.” That ruling is the bedrock on which every RERA order execution now rests.

Step One: Obtaining the Recovery Certificate

An execution or recovery application should be filed with the Authority or the Adjudicating Officer who passed the order, along with a certified copy of the order, proof that the appeal period has lapsed or that no stay operates, and a precise computation of the sum due. The Authority then issues a RERA recovery certificate quantifying the debt and forwards it to the District Collector where the builder’s assets or project lie.

Step Two: Recovery by the District Collector

Once the certificate reaches the Collector, the matter moves into the revenue machinery. The Collector treats the sum like unpaid land revenue and can attach and sell the builder’s property, freeze bank accounts, and issue demand and distress notices reaching the developer’s assets directly. The certificate opens the door; active follow-up and pointing the Collector to specific attachable assets is what brings the money home.

What If the Builder Still Doesn’t Pay?

Non-compliance by the builder has its own penalties. Section 63 of the Act deals with the situation wherein a promoter who fails to comply with an order of the Authority is liable to a penalty for each day the default continues and cumulatively extends up to five per cent of the estimated cost of the project. Section 64 exposes the promoter to imprisonment of up to three years, or a fine of up to ten percent of the estimated project cost, or both. There have also been situations where the allottees have also approached the High Court under Article 226 when the authorities have been slow to act on a recovery certificate.

Practical Learnings

  • Checking whether the 60-day appeal period has ended or whether no stay has been granted by the Appellate Tribunal to confirm that the order is final.
  • Filing the recovery/execution application before the Authority or Adjudicating Officer, together with a certified copy of the order and a correct computation of the amount due.
  • Obtain the recovery certificate and ensure it is forwarded to the correct District Collector—the one who has jurisdiction over the builder’s assets or the project.
  • Follow up with the Collector’s Office and identify specific attachable assets or bank accounts of the builder.
  • If recovery is stalled, Section 63/64 penalties can be pressed, along with a writ petition to compel time-bound execution.

Conclusion

A RERA order is valuable only if you have the ability to enforce it. However, the statute, backed by the decision in Newtech Promoters, gives homebuyers a powerful route: the amount due is recoverable from the builder as an arrear of land revenue, through a recovery certificate executed by the District Collector, with escalating penalties for continued default. The process rewards persistence, precise computation, the right certificate sent to the right Collector, and steady follow-up.

Author: Namanveer Singh Sodhi, Associate,
Co-Author: Aditi Chauhan, Intern